Slow Pace Continues for Hudson Site Project
Dan Gilbert’s Hudson site project broke ground in December 2017. The original plan intended the tower to be taller than the RenCen, but even after the downsizing of its planned tower, it’s a long way from being complete. According to experts, it takes about four to five years to build big skyscrapers in the U.S., yet the Hudson site development is moving slower than recent projects in Chicago with higher towers. The pandemic’s negative impact on the demand for office space, more hotel rooms and more luxury apartments may be factors in the slow pace of construction. According to Mayor Mike Duggan, people who have office buildings are rethinking the amount of office space they’re using. Convention business has also been impacted. Downtown hotel occupancy was 36% in September, 34% drop from the previous year. The $900 million-plus project had an original completion date of summer 2022.